2>C£ 23/4^ STUDY ON STRUCTURAL ASPECTS OF UNDERPASSES IN SOUTHERN TRANSPORT DEVELOPMENT PROJECT The thesis submitted to the Department of Civil Engineering of the University of Moratuwa in partial fulfillment of the requirements for the Degree of Master of Engineering in Structural Engineering Design. LIBRARY" !l*IVfrRSIYV Of MORATUWA, SR! LAK.v< V.QRATUWA By V.G. Liyanagamage Research Supervised By Prof. M. T. R. Jayasingha University of Moratu>va 93912 DEPARTMENT OF CIVIL ENGINEERING UNIVERSITY OF MORATUWA SRI LANKA. Semptember 2009 93 9/z (■' :•I - 4 & 6 >4- i) 93312 Abstract ABSTRACT The Colombo-Matara express highway also known as the Southern Lanka Express Highways or simply the Southern Expressway is a highway currently under construction in Sri Lanka. The 126 km long highway will link the Sri Lankan Capital Colombo with Matara, a major city in the Southern Province of the Island. Construction of the highway began in 2006 and it is expected to be completed in 2010 at the cost of $600 million. When completed, it will reduce the time taken to travel from Colombo to Matara to one and a half hours from the current four hours. It is known fact that the Southern Highway and other subways linked with are normally supported by a wide range of different structures which require careful thought in selecting a suitable one for each location. In fact, these structures form a vital part of transport infrastructure and the smooth running of the network as designed. Even though, this study has been narrow down only to underpasses from the vide range of structures being used. Therefore, in this research work, it is mainly focused on to the underpasses such as metal and concrete underpasses used in and its significant impact on the cost initiatives, suitability and the environmental impacts and etc. The technology used for the metal underpasses on this project is new to Sri Lanka. Traditionally in Sri Lanka, pre cast concrete structures are the preferred option, however, in this project, metal underpasses has also been used. The introduction of new technology requires knowledge of their structural behavior, particularly when used in combination with other materials, and their long-term durability. Over the last years, many structures have started to show signs of degradation and deterioration as a result of the high chlorate content in the air in southern Sri Lanka and some kind of crack failures due to bad workmanship as well as lack of adequate supervision. All these issues has been discussed and concluded in this report in a precise manner based on physical observation and on literature survey. i Abstract Finally, this research concludes that the use of concrete box underpasses in the southern highway is mostly substantiated with country like Sri Lanka due to its inherent characteristics and with the economy and the durability concerns. In fact, this report is a part of a post contract analysis which describes important facts that had to be emphasized in selection of the structure underpasses for Southern highway project and concluded which type of underpasses would have been used with the great economic impact to Sri Lanka. ii Acknowledgement Acknowledgement I would like to make this opportunity to forward my sincere thanks to the project supervisor, Prof. M.T.R. Jayasingha who helped me to make this project a success by giving advice and looking in to the problems encountered. His guidance and constructive criticism helped me o execute the project successfully. I wish to thank the Vice Chancellor, Dean of the Faculty of Engineering and the Head, Department of Civil Engineering for allowing me to use the facilities available at the University of Moratuwa. I am grateful to the RDA for the leave granted to me to follow the postgraduate degree course. I wish to thank to Dr. I.R.A.W. Weerasekara, course coordinator and Dr(Mrs) M.T.P. Hettiarachchi, the research coordinator of the project for the encouragement given to me in completing this study, and all the lecturers of the postgraduate course on Structural Engineering Design who helped me to enhanced my knowledge. Special thanks go to Mr. L.G. Sirisena, Mrs. V.B. Panditha, my loving parents, for the support given for my education and learn to be confident throughout the career. I also would like to thank my husband for giving valuable support and encouragement to complete the study during the period. Finally, I gratefully acknowledge everybody who helped me in numerous way in completing my research study. V.G. Liyanagamage. August 2009. iii Declaration DECLARATION I, V.G. Liyanagamage, hereby declare that the content of the thesis is the output of the original research work carried out at the Department of Civil Engineering, University of Moratuwa. Whenever others’ work is included in this thesis, it is appropriately acknowledged as a reference. V V^CXCja. ...Qk/.!flJ. .... Signature Name of the Student Date Signature Name of the Supervisor Date iv Contents Pages Abstract.................. Acknowledgement Declaration............ 1 m IV Contents......... List of Figures List of Tables. v vm IX 1Chapter 1.......... 1.0 Introduction 1 11.1 General.................................................... 1.2 Main Objectives..................................... . 1.3 Methodology........................................... 1.4 Main Findings......................................... 1.5 Arrangement of the Report..................... Chapter 2....................................................... 2.0 Literature Review.................................. 2.1 Applications of Corrugated Steel Products 2.2 Description of Corrugations..................... 2.3 Structural Properties of Conduit Wall...... 2.4 Pipe Seams............................................. 2.5. Minimum Cover Requirements.............. 2.6. Normal Bedding..................................... 2.7. Camber.................................................. 2.8. Selection of Structural Backfill............... 2.9. Vertical Deflection................................. 2.10. End Protection...................................... 2.11 Failures in Metal structures.................... 6 6 7 7 8 8 8 9 11 11 12 12 13 14 15 16 16 v 172.11.1. Buckling of the conduit wall..... ...................... 2.11.2. Bolt hole tears............................................. . 2.11.3. Bearing failure at longitudinal seams.............. 2.11.4. Excessive deformation of conduit cross section 2.11.5. Collapse of the structure................................. 2.11.6 Remedial measures......................................... Chapter 3................................................................. . 17 17 17 18 18 19 193.0 FIELD SURVEY 193.1 Introduction............................................................. 3.2 Method and work Procedure..................................... 3.2.1 Metal Structures................................................ 3.2.1.1 Filling and Excavation.................................... 3.2.1.2. Foundation Preparation.................................. 3.2.1.3. Camber at Installation.................................... 3.2.1.4. Erection of Structures.................................... 3.2.1.5. Backfilling..................................................... 3.2.1.6 Shape Control................................................. 3.2.1.7 End Treatment................................................ 3.2.2 Box Culvert...................................................... 3.2.2.1 Filling and Excavation................................... 3.2.2.2. Construction of Box Culverts........................ 3.3. Failures in Metal Underpasses................................. 3.4 Summary................................................................. Chapter 4........................................................................ 4.0 Analysis of Metal Structure & Results................ 4.1 Introduction............................................................. 4.2 Description of Loads on the Metal Structure............. 4.2.1 Dead Load....................................................... 4.2.2. Live Load HB Loading................................... 4.3. Design Calculation as per AASHTO (For HPA 74N) 4.3.1 Description of the Proposed Structure................ 4.3.2 Outline Drawing of the Proposed Structure......... 4.3.3. Design Pressure................................................ Chapter 5........................................................................ Analysis of Box Culvert, Results & Design.............. 5.1 Introduction............................................................. 5.2 Load Cases........................................................ 19 19 19 20 20 20 20 21 21 21 21 22 22 24 25 25 25 25 25 26 26 26 27 27 31 31 ...31 31 U4 Vvi 325.3 Loads on the Box Culvert 325.3.1 Loads due to soil.............................. 5.3.2 Live Loads...................................... 5.3.3. Loads on the top slab....................... 5.3.4. Loads on the side walls................... 5.3.5. Loads on the bottom slab................. 5.3.6 Horizontal Live load due to traction... 5.3.7. Hydrostatic Pressure....................... 5.4 Modeling of Box Culvert........................ 5.4.1 Load Calculation.............................. 5.4.1.1 Dead Load Calculation.................. 5.4.1.2. Live load calculation.................... 5.4.1.3. Super Imposed Dead Load............ 5.4.1.4. Reaction from Soil Calculation...... 5.4.1.5 Lateral earth pressure calculation .... 5.4.1.6. Traction force............................... 5.4.1.7. Hydrostatic Pressure.................... 5.5 Concrete Outline Drawing of Box Culvert 32 33 33 33 33 33 34 34 34 34 35 36 41 42 42 43 435.6. SAP2000 model of the Box Culvert 445.7 Load Combinations 445.8 Deformed Shape for Load Case 4.3... 5.9 Results from the SAP2000 Modeling Chapter 6........................................ 6.0 COST ANALYSIS.................... 45 47 47 476.1 Introduction.............................. 6.2 Cost Estimating Process............ 6.3 Cost Analysis of Metal Structure 6.4. Cost Analysis of Box Culvert.... 6.5 Cost Saving.............................. 47 47 49 50 51Chapter 7............................................................... 7.0 CONCLUSIONS AND RECOMMENDATION 51 52REFERENCES 53APPENDIX -A vii List of Figures Page 2Figure 1.1 : View of a Metal Structure............................................. Figure 1.2 : View of a Box Culvert.................................................. Figure 1.3 : Typical Details of Metal Structures.............................. Figure 2.1 : (a) Longitudinal Stiffeners (b) Transverse Stiffeners Figure 2.2: Types of Corrugations available.................................... Figure 2.3: Sectional Properties of Selected Corrugation............... Figure 2.4 : Typical Flat Bedding..................................................... Figure 2.5 : Typical Vee Shaped Bedding........................................ Figure 2.6 : Cambered pipe............................................................... Figure 2.7 : Typical Vertical Deflection.......................................... Figure 3.1 : Husker walls are cracked.............................................. Figure 3.2 : Weeds comes through the plates of Metal Structure... Figure 3.3 : Plates are Corroded...................................................... Figure 4.1 : Concrete Outline of the HPA74N................................ Figure 5.1 : Loads on the Box Culvert............................................. Figure 5.2 : HB Vehicle Wheel Arrangement.................................. Figure 5.3 : Concrete Outline of Box Culvert.................................. Figure 5.4 : Model of Box Culvert.................................................. Figure 5.5 : Deformed shape of Mode 1.......................................... Figure 5.6 : Deformed shape for Mode 2........................................ 2 4 8 10 11 13 13 14 15 22 23 23 27 32 35 43 43 44 45 viii List of Tables Page 12Table 2.1 : Ultimate Seam Strength for MP152 Corrugated Structures Table 4.1 : Description of the Proposed Structure.............................. Table 5.1 : Results from the SAP2000 Modeling............................... 26 46 ix Chapter 1 Introduction Chapter 1 1.0 Introduction 1.1 General Traffic safety concerns, the use of underpasses and Overpasses are now increasingly being adopting in the highway construction in Sri Lanka. When the Southern Transport Development project is concern, the design professionals have adopted these features with a great attention to cater the smooth transport with a safe and without undue delays. In this scenario, various types of underpasses have been integrated along with the road lines and crossings. Those are bridges, metal structures, box culverts and pipe culverts. In the designer’s point of view, there are several issues that have to be concerned in selecting a typical underpass to the highway project. Some fundamental issues governing under these criteria are type of road users, cost, method of construction, Procurement of construction materials as well as availability, durability and the environmental issues. Metal structures and box culverts occupied in roads play a major role as replacement for the bridges as well as the cost significant alternative. Following advantages could have been encountered when such a structure is incorporated with the roads. • No bridge deck deterioration problems. • Eliminates constant maintenance of bridge approaches and painting of superstructure. • Permits use of constant roadway section in the vicinity of structure. • Roadway easily widened by simple extension of ends. • Readily available - components are standard shop items - can be field assembled with unskilled labour. • Less design and construction time - total project completed earlier. • Environmentally acceptable - permits natural appearance of earth slope and vegetation to be utilized. 1 Chapter 1 Introduction In Southern Transport Development Project we mainly identify two types of underpasses. Those are metal structures and box culverts. Fig. la shows the front view of a metal structure and Fig. lb shows view of a box culvert. Figure 1.1: View of a Metal Structure j Figure 1.2 : View of a Box Culvert 2 Chapter 1 Introduction Metal Underpasses In relation with the Southern Transport Development project, there are five types of metal underpasses. Curved corrugated metal plates have mostly used for this metal underpasses. Those are MAUP 47N, MAUP 55N, MAUP 67N, HPA 60N, HP A 74N & HES 87N. Figure 1.3 shows the typical drawings of metal structures mentioned above. The selection of the type depends specially on the maximum span & rise. Moreover, the Span & the rise depend on the design elevations of the secondary road which passes through the structure and the type of vehicles using that secondary road. Structural design of metal underpasses is in accordance with the Standard Practice for Structural Design of Corrugated Steel Pipe , Pipe Arches and Arches for Storm and Sanitary Sewers and Other Buried Applications (ASTM A 796/A 796-01). Dimensions and tolerances is in accordance with Standard Specification for Corrugated Steel Structural Plate, Zinc - coated, for Field - Bolted Pipe, Pipe - Arches and Arches (ASTM A761/A 761M-02). 3 Chapter l Introduction i . 50CO ! \ s I:: 2p /\ ■- wr,i czzri Mrtm] MAUP No .4 7N HPA N0.6OM i i i VIg aww-:e S . Ml* VS i HPA No.74NMAUP No.55N SZc 3C0Q 1 I so I MAUP No.67N Figure 1.3 : Typical Details of Metal Structures 4 Chapter 1 Introduction Box Underpasses The size of the box underpasses varies with the fill height and the type of vehicles traveling on the secondary road. Major material used in box underpasses is ready mixed concrete - class 30/20. The structural design of the box underpass is in accordance with BS 8110. In box underpasses there is a significant moment carried by the surface of the box underpass. Need For the Research Work Southern Transport Development project begins at mid of year 2002. It is important to list out following failures based on recent physical observation of site visit, • Corrosion of metal structures . • Movements of metal structures plates. • Absence of Nails used to connect metal structures plates. • Cracks in box culverts. • Cracking in husker walls of metal structures. The above structures have been designed for a life time of 100 years. However, the above mentioned defects have been noted with in a period of four years after the construction. Road was not opened to traffic during this period (i.e. structures have not subjected to design loads) 5 Chapter 1 Introduction 1.2 Main Objectives To obtain field surveys and analytical research data that can substantiate specification for the selection of most effective type of underpasses in modem highways as a means to reduce wastage occurred due to use of ineffective type of underpasses by considering the structural aspects. 1.3 Methodology In order to achieve the above objectives, the following methodology was adopted: 1. A literature review was conducted to determine the desirable features that should be adopted in construction of metal underpasses and box culverts. 2. Field survey to evaluate current condition of structures. 3. A comparison was made for the structural forms recommended for the underpasses by means of reaching compromise solutions. 4. A comparison was made by designing the metal structure manually and box culvert in SAP 2000 to find the most effective type of underpass that can be resist vertical and horizontal loads. 5. Cost comparison was carried out between metal structure and box culvert 6 Chapter 1 Introduction 1.4 Main Findings The main findings of this research can be presented with respect to structural forms, structural detailing and cost implications. 1 The Construction of Box Culvert is more cheaper than the construction of Metal Structure. 2 Box culvert is more durable than the Metal Structure 1.5 Arrangement of the Report This report is presented in the following manner. Chapter 2 presents a detailed literature review made to determine the desirable features that should be adopted in construction of metal underpasses and box culverts. Chapter 3 deals with the field visits made and the detail description about the site condition. Chapter 4 presents the design of metal structure and the results Chapter 5 deals with the analysis of box culvert and the design. Chapter 6 presents the cost comparison between metal structure and box culvert. Chapter 7 presents the conclusions made from the research. 7 Chapter 2 Literature Review Chapter 2 2.0 Literature Review 2.1 Applications of Corrugated steel products Corrugated steel products have been used for over 75 years play a major role in the modem engineering technology for a wide range of important functions. Flexible steel conduits play an important role in the form of culverts, storm sewers, subdrains, spillways, underpasses , conveyor conduits and service tunnels: for highways, railways, airports. In the late 1960’s , developments were made which involved adding longitudinal and circumferential stiffening members to the conventional corrugation structural plate structures that permitted the use of larger sizes and increased permissible live and dead loads. The above two types of stiffeners are shown in Figure 2.1. il • f' Figure 2.1 : (a) Longitudinal Stiffeners (b) Transverse Stiffeners (Ref. : Design and Construction of Soil Steel Bridges, George Abdel - Sayed) Some of the applications in which these structures are serving are bridges, highway and railway overpasses or underpasses, stream enclosures, tunnels, culverts and conveyor conduits. These structures have been popular for bridge replacement, and when used as such provide the following advantages: 8 Chapter 2 Literature Review No bridge deck deterioration problems. Eliminates constant maintenance of bridge approaches and painting of superstructure. Permits use of constant roadway section in the vicinity of structure. Readily available - components are standard shop items - can be field assembled with unskilled labour. Less design and construction time - total project can be completed earlier. Less construction engineering and field inspection. Environmentally acceptable - permits natural appearance of earth slope and vegetation to be utilized. Minimum delay to earth moving or other construction operations. Least affected by weather and temperature. 1. 2. 3. 4. 5. 6. 7. 8. 9. 2.2. Description of Corrugations Types of corrugations available are shown in Figure 2.2. Corrugations commonly used for pipes are termed circular arcs connected by tangents, and are described by pitch, depth and inside forming radius. Pitch is measured at right angles to the corrugations from crest to crest. For corrugated plate, the thickness shall be measured on the tangent of the corrugations. The thickness shall include both the base metal and the coating. 9 Chapter 2 Literature Review Figure 2.2: Types of Corrugations available In Southern Transport Development Project they have used 6 by 2 in (152 by 21mm) corrugation. The above corrugation is the Standard of the American Association of State Highway and Transportation officials. 10 Chapter 2 Literature Review 2.3. Structural Properties of Conduit Wall Sectional properties of the arc - and - tangent type of corrugation are derived mathematically. Research by American Iron and Steel Institute has shown that failure loads in bending and deflection within the elastic range can be closely predicted by using computed sectional properties of the corrugated sheet. Figure 2.3 shows the sectional properties of selected corrugation for the Southern Transport Development Project. Ultimate Strength of Bolted Structural Plate Longitudinal Seams in kN per m __________ of Seam___________ RadiusTangent Length ,Tl. Area of Section/*. mm2/mm Tangent Angle Moment of Inertia.mm 4/mm Specified ;Thickness ofGyration ,r,mmA0 2 Bolts per Corrugations 3 Bolts per Corrugation I (mm) 4 Bolts per Corrugation mm 2 82 Hi- 3.29 48.00 44 47 990.06 17 30 613 00 4.24 47.27 44 73 1280.93 17.40 905.00 5.18 46.43 45.00 2575_89 1769.80 17.40 1182.00r 4.79 5.80 45.90 45.18 17.50 1357.00 ! 5.54 6.77 45.03 45.47 2Q79.B0 17.50 1634.00 632 7.74 44.15 47.77 2395.25 17.60 1926.00 l 7.11 8.72 43.23 46 09 2717.53 17.70 2101.00 2626.00 2830.00 808 989 41.99 46.47 3113.54 17.70 3430.00 11.88 " 40.169.65 47.17 3801.80 17.90 4159.00 Figure 2.3: Sectional Properties of Selected Corrugation (Ref. : ASTM Designation A 796/A 796 M -01, Table 26) 2.4. Pipe Seams Standard method of shop - fabricating the seams of annular corrugated steel pipe and pipe - arches are; • Riveted Seams • Spot welded seams • Bolted Seams and joints In Southern Transport Development Project they used bolted seams of 3/4in diameter (high strength hexagonal bolts meeting ASTM A 449) Following seam strength values are based on a seams using 3A” bolts with heavy hex. heads spaced at 13.12 bolts per 11 Chapter 2 Literature Review meter. These are designed for fitting either the crest or valley of the corrugations, and to give maximum bearing area and tight seams without the use of washers. Table 2.1 describes the ultimate seam strength values for MP 152 corrugated structures. Specified Thickness (mm) Seam Strength (kg/m) 2.82 63,217 3.56 84,830 6.0 182,061 Table 2.1 : Ultimate Seam Strength for MP152 Corrugated Structures 2.5 Minimum Cover Requirements Where pipe is to be places under roads, streets or free ways, the minimum cover requirements shall be determined. Minimum cover is the distance from the top of the pipe to the top of the rigid pavement or to the top of subgrade for flexible pavement. 2.6 Normal Bedding Pressures developed in the shell by the weight of the backfill and live loads are transmitted both to the side fill and strata underling the pipe. The bedding is the portion of the foundation in contact with the bottom or invert of the structure. Depending upon the size and type of structure, the bedding may either be flat or shaped. With flat bedding, the pipe is placed directly on the fine graded upper portion of the foundation. For pipe - arches and large span structures, with invert plates exceeding 3700mm in radius, the bedding should be shaped to the approximate profile of the bottom portion of the structure. Alternatively, the bedding can be shaped to a slight vee shape. Typical details of flat bedding and vee shaped bedding are shown in Figure 2.4 and Figure 2.5 respectively (Ref.: Installation & Backfilling Standards for Armco Structures). 12 : Chapter 2 Literature Review o' struojfi; bacMti :£5J Jo 200 T.r’. Jhick, CCnTOCW*. Mud ACWIWOI &CC<1 ~J &TVnr~* \ -A , -V H nc^ybf SesxWl 3& 3«±S. 1' T% ** v*' C? SSfsCfc-? -3 O'* ---r,’~£.V~ **fvcJw«? is crrsl-jr.~ 7 • ? SJniCUl* e^cxJill OcntpiCf'J UrttJc* i'.-iur-rr^fi.rine Grtvd««i &iac Figure 2.4 : Typical Flat Bedding 30 Ro'julnr Backfill fj.'li .if Slit l3u«:.V!i-f ”-v ;c 30C sv r.i I Ihicfc. C«5tlWJCHrJ ^ (JCSii Med. A&&») 4» — i i RyyuUjf SackHU or ’.IS-nj.'IU SchI 0 — ^. 4JII _ ---------- -----------|XKJ-*m Mod. AusMc*M ti-' Corner ^ic.-eSedCinq iiil. utKOdioacS&J up :g 300 nun thicwvais. fin^odcd to :;lidOO of do&orn <*.4 poc-arcx f20—fJ5V» Mod. Aasftio) Figure 2.5 : Typical Vee Shaped Bedding 2.7 Camber The soil cover above the conduit varies along the pipe because of embankment slopes . Due to this uneven cover, the foundation under the pipes settles more under the middle length of the conduit than under the outer length. Longitudinal profile of the bedding must account for this uneven settlement. Camber is simply a rise at the center of a culvert 13 ■ Chapter 2 Literature Review above a straight line connecting its ends to avoid a sag in the longitudinal profile of the culvert. A cambered pipe is shown in figure 2.6 (Ref. : Installation & Backfilling Standards for Armco Structures). Camber Final Qra.rJe alter settlement Figure 2.6 : Cambered pipe 2.8 Selection of Structural Backfill Requirements for selecting and placing backfill material around or near the conduit are similar, in some respects , to those for a roadway embankment. However, a difference in requirements arises because the conduit may generate more lateral pressure than would the earth within the embankment if no structure existed. Therefore soil adjacent to the conduit must be compacted densely. The Structural backfill material should conform to the following classification (Installation & Backfilling Standards for Armco Structures); • Minimum Grading Modulus : (G.M.) 0,8 • Maximum Plasticity Index (P.I) 10 + 3 G.M. • Minimum CBR at compacted density 15% • Minimum Compacted Density (MOD. AASHTO) 90% • Maximum % passing 75 micron sieve 40% The backfill material should be placed and compacted in layers not exceeding 300mm of compacted thickness, with each layer being compacted to the required density at the 14 Chapter 2 Literature Review optimum moisture content. Backfill material must be placed equally on each side. Each layer must be compacted to specified density before adding the next layer. Care must be taken to ensure that no more than one layer difference each side of the structure. Controlling the symmetry of the structure is another important thing during backfill operation, by control of the backfill operation. As a general rule, no deflection in any direction greater than 2% from original shape should be allowed during the backfill operation (Installation & Backfilling Standards for Armco Structures). 2.9 Vertical Deflection Corrugated steel pipes functions structurally as a flexible ring which is supported by and interact with the compacted surrounding soil. The soil constructed around the pipe is thus an integral part of the structural system. Therefore it is important to ensure that the soils structure or backfill is made up of acceptable material and well constructed. Typical vertical deflection pattern is shown in figure 2.7 (Ref. : Installation & Backfilling Standards for Armco Structures). Fill Load Original ShapeIFinal Shape 1 Ir— A U \ 7 Figure 2.7 : Typical Vertical Deflection Fill material around the structure should be placed alternatively in layers 150 or 300mm thick on both sides. Pipe - arches require that the backfill at the corners (sides) of the best material, and be especially well compacted. 15 i i Chapter 2 Literature Review The above book discuss several points we have to consider when erection of the Metal Structure. • Placing backfill around structure • Shape Control • Vertical Deflection • Construction Loadings 2.10 End Protection This is the case with any water carrying structure, the compacted fill material around an Armco structure has to be adequately protected against erosion. This protection can take the form of concrete headwall and wing walls, stone pitching, gabion mattresses or concrete slab protection of the embankment. The Standard concrete ring beam recommended for Armco Structures should form an integral part of the end protection of a structure. There is no substitute for adequate end protection. Which ensures that compacted fill will not be damaged by erosion or flooding. 2.11 Failures in Metal structures Bad construction practice is the main reason for the failure of those structures. The lack of understanding of the mechanics of behavior of these structures promotes bad construction practice. Common forms of failures are: • Buckling of the conduit wall. • Bolt hole tears. • Bearing failures at longitudinal seams. • Excessive deformation of the conduit cross section’ • Lifting of the invert 16 Chapter 2 Literature Review • Lifting of the pipe ends. • Distortion of the pipe ends. • Collapse of the structure. 2.11.1. Buckling of the conduit wall Buckling can be a result of a local buckling in which the metallic shell buckles in to a large number of waves, each of relatively small length. Buckling can occur in the compression zone of the wall section. When the conduit wall undergoes large bending deformations, this can be usually take place in conduit segments of relatively small radius of curvature. 2.11.2. Bolt hole tears Bolt hole tears are caused by excessive bending of the plates, and that the tendency to develop the cracks is directly related to the tension in bolts. 2.11.3. Bearing failure at longitudinal seams Bearing failure at longitudinal seams can take place due to the yielding of the conduit wall directly under the bolts. This type of failure takes place under excessive conduit wall thrust. 2.11.4. Excessive deformation of conduit cross section This is the most common from of failure in metal structures. This result in poorly compacted backfill, backfill containing large quantities of clay or organic matter and well compacted and good quality backfill not extending on either side of the conduit. Excessive pipe deformation do not always develop after the structure has been built. It deform during the initial stages of the backfilling operation.can 17 Chapter 2 Literature Review 2.11.5. Collapse of the structure This is the most dramatic failure in these type of structures. The failure of metal underpasses is more common than other type of underpass (Design and construction of Soil steel Bridges, George Abdel-Sayed ). The failure of the metal underpass could have been avoided by careful construction, using good - quality backfill and employing good construction practice. Factors that lead to the collapse of metal structure are as follows: • Use of poor quality soil,(containing large quantities of clay and organic matter, in the backfill) • Compaction of backfill in very thick layers. • Compaction of backfill in cold weather. 2.11.6 Remedial measures The various methods that can be used as follows (Design and construction of Soil steel Bridges, George Abdel-Sayed). • Temporary props. • Partial concreting inside conduit. • Internal grouting. • Shortcreting. • Partial concreting outside conduit. 18 . i UNivtMsrrv if wmimKuw • ■rtQHATUWA Chapter 3 Field Survey Chapter 3 3.0 FIELD SURVEY 3.1 Introduction This chapter describes the observations made during field survey. It describes detail description of the backfilling, construction of foundation, installation of metal structure / box culvert, backfilling, shape control, end treatment and the failures in the site. 3.2 Method and work Procedure 3.2.1 Metal Structures 3.2.1.1 Filling and Excavation Filling and excavation width vary with the type of soil, a) In Embankment Fill - Firm Foundation Embankment filling & compaction will be carried out in layers. In fill sections, before excavation is begin, the fill shall be constructed for a distance of 3 span / diameter and on each side of the metal structure to a minimum height of 25% of the vertical dimension of the metal structures. b) In Embankment Fill - Soft Foundation The Engineer will be required to issue his instruction. Soft ground treatment works will be carried out in accordance with the Engineer’s instructions. c) In Cut - Firm Foundation (Soil) The width of the excavation shall be 2m minimum each side of the structure. d) In Cut - Rock Foundation Excavation by blasting in accordance with the blasting pattern. e) In Cut - Soft Foundation Limits of the excavation shall be 2m minimum each side of the structure. 19 C3S12 Chapter 3 Field Survey 3.2.I.2. Foundation Preparation • MAUP and HES structures shall be placed on a uniform stable earth or granular foundation. • HPA structures are founded on reinforced concrete footings. 3.2.I.3. Camber at Installation Cambering shall not be executed for the structures with concrete components (Thrust beams / footings) and in such cases foundation shall be constructed so as to avoid settlements. That is cambering shall be applicable for MAUP structures only. 3.2.1.4. Erection of Structures MAUP structures shall be assembled in 4 stages, i.e. bottom, comer, side and top. HPA and HES structures can be assembled in 3 stages, i.e. Side, comer and top. In every type of structure plate assembling shall be proceeded at one side and the other side alternatively. 3.2.I.5. Backfilling Structural backfill material specified in specifications shall be used as backfill material. The main deciding factor for selecting backfilling material shall be the bearing pressure of the material compacted to specified density. Placing of backfill shall be carried out equally on both sides of the structure, in layers of compacted thickness of 300mm each layer shall be compacted to specified density before placing the next layer. 20 Chapter 3 Field Survey 3.2.1.6 Shape Control This refers to controlling the shape and symmetry of structure during backfilling by control of the backfill operation. Care must be taken while installing the structure. 3.2.1.7 End Treatment Reinforced concrete shall be provided at the ends of the structure. Protection to the embankment shall be provided by concrete headwall and wing walls or gabion mattress protection. 3.2.2 Box Culvert 3.2.2.1 Filling and Excavation Filling and excavation width and the depth vary with the type of soil. In Embankment Fill - Firm Foundation The filling distance and height will vary with the structural dimentions and existing elevation of the location. a) In Embankment Fill - Soft Foundation Soft ground treatment works will be carried out in accordance with the instructions. b) In Cut - Firm Foundation (Soil) For Box culverts in soil foundation, additional excavation of 75mm below the bottom level of the culvert is needed for blinding layer. In Cut - Rock Foundation Excavate by blasting in accordance with the blasting pattern. c) d) 21 Chapter 3 Field Survey e) In Cut - Soft Foundation The excavated area will be backfilled with the suitable material and compacted up to the 300mm above the bottom of the box culvert. 3.2.2.2. Construction of Box Culverts Formwork - class 1 will be fixed for placing concrete for base slab of box culvert. The formwork of the base slab will be removed 25hrs after concreting. Curing of all exposed concrete surface will be carried out for 7 days. 3.3. Failures in Metal Underpasses Southern Transport Development project begins at mid of year 2002. But there were vide variety types of failures can be observed in the site. Figure 3.1 : Husker walls are cracked. 22 \ Chapter 3 Field Survey Figure 3.2 : Weeds comes through the plates of Metal Structure. Piute Discoloured IMS - HPA74N [Cha. (a 5+258 02-11-2007 Figure 3.3 : Plates are Corroded.. Most recently Contractor of the Southern Transport Development Project started to undergo some rectification methods. 23 Chapter 3 Field Survey 3.4 Summary To ensure that the steps of the procedure are fully complied with during the activities such as setting out, excavation, embankment filling, bedding, erection and backfilling etc. certain inspections and verifications will be carried out as described in the above procedures. 24 Chapter 4 Design of Metal Structure Chapter 4 4.0 Design of Metal Structure 4.1 Introduction The designs are carried out to American Standards / Practices as listed below. Traffic loading has been calculated according to BS5400 Part 2, HA & HB 30 units as requested by Road Development Authority. Design Calculations are in accordance with following references: 1. Handbook of Steel Drainage & Highway Construction Products ( American Iron & Steel Institute) 2. ASTM Designation A 761/A 761M-98 - Corrugated Steel Structural Plate , Zinc - Coated, for field - Bolted Pipe, Pipe - Arches and Arches. 3. ASTM Designation A 796/A 796M-01 - Standard Practice for Structural Design of Corrugated Steel Pipe, Pipe Arches and Arches for Storm and Sanitary Sewers and other Buried Applications. 4. Standard Specifications for Highway Bridges (AASHTO) - Section 12 5. British Standard for Steel, Concrete and Composite Bridges - BS5400 Part 2 : 1978. 4.2 Description of Loads on the Metal Structure 4.2.1 Dead Load The following unit weight of materials were used for the design • Compacted Density of Asphalt Concrete Surfacing - 24.030 kN/m3 • Compacted fill ( Soil) - 19.0 kN/m3 25 Chapter 4 Design of Metal Structure 4.2.2. Live Load HB Loading As per BS5400; 16 wheels, each 75kN ( 30units of HB ) as shown in Figure 11 of BS5400 with innermost axels 6m apart shall be considered. Accordingly the square contact area shall be 261mm a side. 4.3. Design Calculation as per AASHTO (For HPA 74N) 4.3.1 Description of the Proposed Structure (a). Structure Type HPA 74N/ Armco MP152S Dimensions(b). Max. span 10.58m x rise 5.42m (c). Top Radius 7.32m Comer Radius 1.65m(d) 152mm x 50.8mmCorrugation(e) 6.32mm (Armco Nominal Thickness 6.35mm)(f) Specified thickness - Top Arc 6.00mm (Armco Nominal Thickness 6.00mm) Specified thickness - Remainder(g) Table 4.1 : Description of the Proposed Structure 26 i Chapter 4 Design of Metal Structure 4.3.2 Outline Drawing of the Proposed Structure 600 7 •* ' ■ •. i « ■ V• 4*♦ * 4 f * *4 A v- \m SLOPE COLLARS 600 600C: O ID 'T LONG BOLT 03/4x6'[r105 ■ 0%3% I.7000 97 30 4565 4365 10576 Figure 4.1 : Concrete Outline of the HPA74N 4.3.3. Design Pressure The Design Pressure shall be; P = DL + LL (from AASHTO Section 3.8.2) L 800mm Pavement 900mm Structural Backfill 27 Chapter 4 Design of Metal Structure Dead Load (DL) - (0.9 x 19) + (0.8x24.03) = 36.32 kN/m2 Live Load 261mm x 261mm L J >- 800mm Pavement 900mm Structural Backfill l /77Z /777 kN/m275x9.81Live Load (LL) (0.261+0.7+0.7) x (0.261+0.7+0.7) = 266.68 kN/m2 Design Pressure P = DL + LL = 36.32 + 266.68 = 303.0 kN/m2 The span of the selected type is HPA74N is 10.58m which is more than 6.4m and hence this structure falls in to the category of Long - Span Structural Plate Structures. Therefore the structure is designed in accordance with Subsection 12.7 of AASHTO Section 12. For these structures requirement for buckling and flexibility shall not be applied. 28 Design of Metal StructureChapter 4 According to AASHTO Section 12.1.4.2. The thrust in the wall is ; T = P x S/2 For HPA 74N 10.58mMaximum span (>6.4m i.e. long span structural plate structures) (ASTM 796 Section 5) = 9.81m 5.54m Base span Rise = T = 303.0kN/m2 x (10.58m/2) = 1602.87 kN/m Wall Cross sectional Area (AASHTO Section 12.3.1.) is ; A = _Tl (pfy 1602.87 kN/m— 2 x 310 Mpa = 26 cm2/m = 26.0 cm2/mRequired wall area Area corresponding to the thickness of proposed structure is 74.631 cm2/m. (Thickness 6.00mm) A = 26.0 <74.631 cm2/m Hence ok. 29 Chapter 4 Design of Metal Structure Check as per AASHTO Section 12.7 I.Table 12..7.2.A Minimum Requirement for Long - Span Structures with Acceptable Special Features. In HES 74N Top Radius 7.32m = 24.01 ft Refer Table 12.7.2. A; Top arc thickness = 0.249 in = 6.32mm Specified thickness of Top - Arc of proposed structure = 6.32mm Hence OK. II As per Table 12.7.2.A. The Minimum cover is 4.0ft (i.e. 1.22m for 23 - 25 ft Top Radius & 0.249in Steel thickness ) III According to AASHTO Geometric Limits A . Maximum plate radius = 7.32m = 24. ft < 25ft Hence OK. B. Maximum central angle of Top arc = 80° Central Angle of top arc of proposed structure = 80° Hence OK. C. Minimum Ratio , Top Arc Radius to Side Arc Radius = 2 For Proposed structure Top Arc Radius = 7.32m Side Arc Radius = 1.65m Therefore Ratio for Proposed Structure = 4.436 > 2 Hence OK. Therefore dimensions of the proposed structure satisfied 30 Chapter 5 Analysis of Box Culvert, Results & Design Chapter 5 Analysis of Box Culvert, Results & Design 5.1 Introduction Analysis of Box Culvert was performed in SAP 2000. The box culvert should be designed considering the following issues. • It should be able to discharge the volume expected during a design flood. • The structure of drainage culvert should be designed to be stable against the dead , superimposed dead, live and earth pressure. 5.2 Load Cases Following load cases are to be taken in to account(since culvert is used as underpass) 1. Vehicles at Top - No vehicles at Bottom 1.1 HA only 1.2 HA & HB only 2. No Vehicles at Top - No vehicles at Bottom 2.1 No HA or HB 3. No Vehicles at top - vehicles at bottom 3.1 HA only 3.2 HA & HB only 4. Vehicles at Top & Bottom both 4.1 HA only in top & bottom both 4.2 HA in top & bottom & HB in bottom only 4.3 HA & HB in top & bottom both 4.4 HA in top & bottom & HB in top only \ : 31 Chapter 5 Analysis of Box Culvert, Results & Design 5.3 Loads on the Box Culvert Superimposed dead loaduuuuuuuuu i Live loads uuuuuuuuu Weight of soil Weight of structureuuuuuuuuu > Traction Force Hydrostaticpressure Soil pressure < * A tmtttttt tttttttt Reaction of soil Figure 5.1 : Loads on the Box Culvert 5.3.1 Loads due to soil Depending on the level of the stream, the box culvert can be either at the road level or buried. If it is buried, there will be soil on all four sides. Thus the following loads will act due to the soil: • The weight of the soil between the top slab and the road level acting on the top slab. • The soil pressure acting on the sides of the box culvert. • If there is soil on the top slab, the soil loads will be transferred on to the side walls. 5.3.2 Live Loads Live loads are generally due to vehicles traveling on the road. Live loads are calculated according to BS5400. 32 Chapter 5 Analysis of Box Culvert, Results & Design 5.3.3. Loads on the top slab. Top slab is loaded due to the weight of soil, super-imposed dead load of the road and live loads due to vehicles. 5.3.4. Loads on the side walls This consists of soil pressure and any surcharge pressure due to live loads. 5.3.5. Loads on the bottom slab The soil below supports the box culvert. This soil is loaded due to the weight of the soil above the box culvert, weight of the soil on the top slab, weight of the box culvert and live load on the box culvert. The average upward pressure is assumed on the bottom slab. This pressure is equal to all the loads divided by the bottom slab area. 5.3.6 Horizontal Live load due to traction The structure shall be designed to resist the traction forces. Traction force shall be applied perpendicular to the walls of the box culvert. Traction force was calculated as in accordance with section 6.6 of BS5400 Part 2. 5.3.7. Hydrostatic Pressure The effect of hydrostatic pressure must be taken in to account in the design of box culverts, (either the selected structure is vehicular culvert). Because due to heavy rain if water table increases to the high flood level in that area it will automatically generate high hydrostatic pressure. 33 Chapter 5 Analysis of Box Culvert, Results & Design 5.4 Modeling of Box Culvert Analysis of box culvert was performed using 2D shell elements of appropriate thickness. Soil was modeled as springs. Then the support conditions are taken as simply supported at its two ends. Depending on the SPTN values of each soil type spring constants are calculated and tabulated below. Depth (measured from the culvert top level) (in mm) Spring Constants 2675 8,000 2140 16,000 Below 2140 24,000 5.4.1 Load Calculation 5.4.1.1 Dead Load Calculation Dead load may be calculated from SAP2000 finite element software automatically. 5.4.I.2. Live load calculation HA Loading UDL shall be taken as 30kN per linear meter of notional lane. HA loading for the Top Slab HA loading for the Bottom Slab 30kN/m 30kN/m 34 Chapter 5 Analysis of Box Culvert, Results & Design HB Loading HB loading for the top slab HB loading for the bottom slab 30 units each 75kN 20 units each 50kN ' 38 Chapter 5 Analysis of Box Culvert, Results & Design Load Case 4.2 Total HA load in top & bottom slab 30 x 10.8x2 648 kN = — Total HB load in bottom slab 50 x 4 x 4 1200 kN Super imposed load top slab 7.72 x 10.8 83.38 kN = = Super imposed load bottom slab 7.72x10.8 83.38 kN Volume of concrete {10.8 x ( 0.75 + 0.60 ) x 5.35} + 9 4.7 x 0.5 x 5.35 x 2) 103.148m3 103.148x24 2475.55 kN Weight of concrete = Total downward load 648 + 1200 + 83.38 + 83.38 + 2475.55 4090.30 kN 378.73 kN/mReaction from soil Load Case 4.3 Total HA load in top & bottom 30 x 10.8x2 648 kN slab = = 75 x 4 x 4 1200 kN Total HB load in top slab = 50 x 4 x 4 800 kN Total HB load in bottom slab = = 7.72 x 10.8 83.38 kN Super imposed load top slab =: Super imposed load bottom slab 7.72 x 10.8 83.38 kN = Volume of concrete {10.8 x ( 0.75 + 0.60 ) x 5.35} + 9 4.7 x 0.5 x 5.35 x 2) 103.148m3 = S 39 Chapter 5 Analysis of Box Culvert, Results & Design Weight of concrete = 103.148x24 = 2475.55 kN Total downward load = 648 + 1200 + 800 + 83.38 + 83.38 + 2475.55 = 5290.33 kN Reaction from soil 489.85 kN/m Load Case 4.4 Total HA load in top & bottom slab 30 x 10.8x2 648 kN Total HB load in top slab 75 x 4 x4 1200 kN= Super imposed load top slab 7.72x10.8 83.38 kN = = Super imposed load bottom slab 7.72 x 10.8 83.38 kN = = Volume of concrete {10.8 x ( 0.75 + 0.60 ) x 5.35} + 9 4.7 x 0.5 x 5.35 x 2) 103.148m3 = = 103.148x24 2475.55 kN Weight of concrete = Total downward load 648 + 1200 + 83.38 + 83.38 + 2475.55 4490.30 kN 415.77 kN/mReaction from soil =: 40 Chapter 5 Analysis of Box Culvert, Results & Design 5.4.1.5 Lateral earth pressure calculation Take Surcharge as 10kN/m2 Take Unclassified Soil 18 kN/m3 30 dgrees Y

HB vehicle Apply traction force of 286.4kN from HA vehicle at the center of the notional lane. 5.4.I.7. Hydrostatic Pressure Take the high flood level at the selected culvert area as 4.28m Hydrostatic pressure = hpg = 4.28 x 1000 x 10 / 1000 = 42.8 kN/m2 = 42.8 x5.35x0.5x42.8/42.8 = 114.49 kN/m Equivalent UDL 42 Analysis of Box Culvert, Results & DesignChapter 5 5.5 Concrete Outline Drawing of Box Culvert RFL LINE 5000 : L • < . • i4-V.4. • V25C -a J50mm IHK. approach slab CORBEL 50mm THKTbIJNDING CONCRETE g 8 ------- CONCRETE GRADE 30/20< s 4 500 | >00 m. ____________________ 10500 Figure 5.3 : Concrete Outline of Box Culvert 5.6. SAP2000 model of the Box Culvert fy<- -Vc o-s 'Vs yVV- *-L Ss ^ ~ * ‘ifs Figure 5.4 : Model of Box Culvert 43 Analysis of Box Culvert, Results & DesignChapter 5 5.7 Load Combinations HA Only Dead Weight Earth Pressure Superimposed Dead Live Load = 1.15 = 1.5 = 1.75 = 1.5 HA and HB Dead Weight Earth Pressure Superimposed Dead Live Load = 1.15 = 1.5 = 1.75 = 1.3 5.8 Deformed Shape for Load Case 4.3 ggg||§§ •n i.-1" - mmhA, ^\7\^ \*\ft® l1?; ^ * f-4 f r 7 * r~hrri—s~ j;—j~ y—f— y-hf-f-j -4—4- i-~i *- 1 - 4 ' * 1 j ; - - v ■* # ^ +ib * • > 1 1 1 1—i - > -a- » ' >- >' * '> >i > * *i —i- > * -i i -r—T V *T , \ ' ■ ^ s*> 5 , * dp v -*r \-4^ i i i i 3 «^ s'- : ' 1 1 > 1 "if' -V 3’ 1 * i i i I 1 : 3 Figure 5.5 : Deformed shape of Mode 1 44 Kv->» Chapter 5 Analysis of Box Culvert, Results & Design : - '©©V awaM «!*.' \ >/, . 1 V. SM I A™ \ 9\t i i \ v,\\ * * -. v. ., ^ V r J 7 _.•* I* ? f f f ? 5 } * 4 4 3 1 i, ^7 hV' ■Ml/'.^r 7 > , 7s 7 - f f -s~ t ? 4—1—a—7—i—i—r—43. w* r f ri'f f'rtrl 17 \ \ \"\ * *1 \/\ ^fTTTTTTTTl' ^ r^TV^T1r*' \ /\ 7' ?P~~£ > ± 7 > f i" 5 —S i~—-f i i * i -i: *:—ifr*. ""©©v / / -r-rTri^r4-H' ^ 1,1 * * ■ * * * ...*k i—>—>---f---J---J---J---f---y-------i---Y~k—7—ir—i— -1; -3—J-— 4- --- -s—1—i—i—i—i—i—i—i-—i—i—i—a—r'Tp w b*-(/- bbb*rb*-' b*-b**(Ab» wb b»-M- V- v b*- h**1 b*-W- \ wb* +b ’rf'. i b*-* V- s—i > b*- V- H- ^ bb W'/ / *> ^ i i S Figure 5.6 : Deformed shape for Mode 2 5.9 Results from the SAP2000 Modeling © ©©■ 45 Chapter 5 Analysis of Box Culvert, Results & Design E SisCDro ^ oj-C cu in u cn r^- | cn cn i cn cn cn m tn o 8ad rd CD cd8 cn8 CDm siraCDacn Ll. 3 3 CDcn cn 8 g3CDCD cncn5cu -^vE E cn CN rd odrn s sSCDcno :z: 5 -* R 8 rn5cn E to jgjij cu in ou_ 3 SICU E E a Z 2 ^ £ S 1 _J 03 Od CJ jy □cn u_ 3 c E 03 -<03 ■>E E a Z 5 -* E ro ^jjj 0) CD a CN U_ 3 1 C E 03 e! a Z 5 -* iE CD ^ 03 -C 03 cd y ! L 3 e E Ie a !Z 5 ^ 03 03i U q«J w! s E ; a .i0303 O T3 3 i[ LJJ LJj... J__1_L———Li. -• 46 Chapter 6 Cost Analysis Chapter 6 6.0 COST ANALYSIS 6.1 Introduction One of the main objectives of this project is to evaluate the cost effectiveness of metal structure when compared with box culvert, to select most appropriate structure type for a site under consideration. This chapter provides guidelines for the establishment of basic cost to compare the alternatives. The basic cost used here is taken form currently used for estimating process at Road Development Authority. 6.2 Cost Estimating Process The process stated below is developed for estimating the underpass cost after the completion of the preliminary design. Cost for all other items including but not limited to the following are excluded from the cost provided in this chapter. 6.3 Cost Analysis of Metal Structure The basic structural items of the HPA74N metal structure was found to be as follows. 47 Chapter 6 Cost Analysis Bill of Material for HPA74N Metal Structure Total Nos. Item Width Length Total Quantity Description Units Height (m)No. (m) (m) HPA74N Metal Plates Nos.1 119 119 Bolts (3/4” x 3”) Nos.2 5219 5219 Unclassified m33 1 14.58 20.13 2231.07.6Excavation Structural Backfill for Metal Structure 1 10.58 20.13 128.000.6m34 1 3.00 20.13 266.04.4 2 1.0 20.13 18.120.45 m3Foundation5 2 (0.45+0.3)72 3.020.2 20.13 2 0.6 20.13 7.250.3 Cost Calculation The basic cost presently used in Road Development Authority was used. Cost of Concrete 1. Grade 30 concrete per m3 with placing 2. Reinforcing Steel (100kg per m3) Rs. 13,000.00 Rs. 15,000.00 Concrete cost with r/f per m3 Rs. 28,000.00 Quantity AmountRate (Rs.) 291,500.00 UnitItem 34,688,500.00119Nos.HPA74N Metal Plates 78,285.00521915.00Nos.Bolts (3/4” x 3”) 1,189,123.002231.0m1 533.00Unclassified Excavation 3,286,992.28Structural Backfill for Metal Structure _____ 3m 394.08342.62 794,920.0028.39TTTm 28,000.00Foundation 40,037,820.28Total Cost 48 Chapter 6 Cost Analysis 6.4. Cost Analysis of Box Culvert The basic structural items of the reinforced concrete box underpass at 09+373 were found to be as follows. Bill of Material for Reinforced Concrete Box Underpass Cross Sectional Area Item Width Length Total QuantityDescription Units Height (m)No. (m) (m) (m2) Grade 30 Structural Concrete 3m1 437.119 Reinforcement Tones 32.3652 Unclassified Excavation 3m 14.30 20.13 7.0 2015.02 1 20.13 6.05 m2 440.85Formwork 20.13 6.053 20.13 9.8 Cost Calculation QuantityRate (Rs.) AmountUnitItem T“Tm 5,682,547.00437.11913,000.00Grade 30 Structural Concrete 32.365 4,854,750.00150,000.00TonnesReinforcement TTTm 2015.0 1,073,995.00533.00Unclassified Excavation 2 440.85 896,334.532033.21Formwork m 12,507,632.63Total Cost Note that the above calculated cost is very basic cost not in the actual cost involving the construction of metal underpasses and box culvert. For the above cost calculation the cost of construction of wing wall, mobilization, 49 Chapter 6 Cost Analysis 6.5 Cost Saving According to the above basic cost calculation the average cost saving for the structural part as follows. Cost saving Rs. 40,037,820.28- 12,507,632.63 Rs. 27,530,187.65 Rs. 27,530,187.65 / 40,037,820.28x 100% 68.7% % of cost saving 50 Chapter 7 Conclusions & Recommendations Chapter 7 7.0 CONCLUSIONS AND RECOMMENDATION According to the cost calculation it is shown that the 74% of cost saving is there by using box underpass. By using box underpass instead of metal underpass Sri Lanka can save billions of money from Southern Transport Development Project. Another useful source of information is the durability of metal underpasses. Sacrificial cathodic protection is the effective method of protecting the metallic shell against corrosion. In this protective system the steel plate is connected through an electrical conductor to a sacrificial zinc or aluminium, plate which acts as anode and corrodes, there by preventing the steel plate from corrosion. 51 References REFERENCES 1. Soil - Steel Bridges, Design and Construction, George Abdel-Sayed, Baidar Bakht, Leslie G. Jaeger. 2. BS 5400 Part 2 : 1978, Steel ,Concrete and Composite Bridges, Specification for Loads , BSI, London, U.K. 3. BS 5400 Part 4 : 1978, Steel ,Concrete and Composite Bridges, Code of Practice for design of concrete bridges , BSI, London, U.K. 4. Armco, Staco, Multi - Plate Super- Span Technical Manual, Access International (Pvt) Ltd., Sri Lanka 5. Installation and Backfilling Standards for Armco Structures, Armco Surperlite (Pty) Ltd. 6. Handbook of Steel Drainage & Highway Construction Products, American Iron & Steel Institute. 7. ASTM Designation A 761/A 761M-98 - Corrugated Steel Structural Plate , Zinc - Coated, for field - Bolted Pipe, Pipe - Arches and Arches. 8. ASTM Designation A 796/A 796M-01 - Standard Practice for Structural Design of Corrugated Steel Pipe, Pipe Arches and Arches for Storm and Sanitary Sewers and other Buried Applications. 9. Standard Specifications for Highway Bridges (AASHTO) - Section 12. 10. User Manual, SAP2000 Nonlinear V8.23, The static and dynamic finite analysis of structures Inc, 1995 Berkeley, Califonia, USA. 11. Foundation Analysis and Design, Joseph E. Bowles 52 APPENDIX -A 53 CalculationReference Output DESIGN OF DECK SLAB (TOP SLAB) Bending moment is critiacl in Load case 4.1. So that consider the loading case 4.1 for reinforcement design. Design main reinforcement for mid span of the slab. Thickness of the slab = 600 mm Part 4: 1990 4.2.3 M = 541 kNm/rrDesign bending moment, M design at mid span 541 kNm/m Assume severe environment condition, Cover Cover= 65 mm = 65 mm Diametre of main reinforcement = 32 mm Effective depth, d = 600-65-32/2 d = 519 mm= 519 mm M = (0.87fy)Asz z = (1 -i.lfyAs/fcubdJd BS 5400 Part 4: 1990 equation 1 equation 5 from these two equations 5.3.2.3 z = 0.5d[1+(1-5M/fcubd2)1/2] z = 0.5d [1+ (1 -5x541x1 06/30x1 000x5232)1/2 ] = 0.908 d < b d Hence o.k Z = 0.908 d = 0.908x519 = 471 mm Main reinforcement As = M / 0.87fyZ = 541x106 7 0.87x460x471 equation 1 mm2/m As req= 2868 == 2868 mm2/m mm2 ) As pro 2925 mm2/m Use T 32 @ 275 (As = 2925 = Check for minimum reinforcement required for cantilever slab Check for minimum reinforcement 100AS / bad = 100x2925/(1000x519) BS 5400 Part 4: 1990 5.8.4.1 = 0.56 >0.15 Main reinforcement T 32 @ 275 Hence o.k fb) DESIGN OF SECONDARY REINFORCEMENT (TOP SLAB) Requirement for secondary reinforcementBS 5400 Part 4: 1990 5.8.4.2 mm2/m(0.12/100)b,d = (0.12/100)x1000x519 = 623 Secondary reinforcement T 12 @ 175 mm2 )(As = 64612 @ 175Use T Calculation OutputReference Serviceasibility Crack check At center of bottom slab maximum service moment 450.5 kNm= 's d= 519 mm 81mrr¥■ /600mm 7 -aep + Njnep(2+aep)x — d Es = 14.2857aep = Ec As 2925 0.005P = ~ 103 x 519bd aep = 14.286 x 0.005 = 0.07143 0.31x— — d 162.56 mmx = 11 xz---- = d3d 464.81 mmz = Service stress, fs = M A,xZ 450.5x106fs = 2925x464.81 = 331.406 N/mm2 = fses = 331.406 = 0.0017 200x103 = fh-x 1 x Gs Es e1 d - x x 0.0017600 - 162.564 523 - 162.564 0.002= ■ em = ei ' b(h-x)2 3EsA,(d-x) = 0.0020336 - 1000 *(600- 162.564 )2 3 x 200 X1000 x 2925 (519 -162.56) : ! 0.002 OutputCalculationReference Calculation of aa Cmin — 81 mm -163cr = V 975+1002 = 123.32 mm 3aCP 8mWa = I + 2[(acr -cm,n)/(h-x)] Wcr = 3 x I 23.32x 0.002 + 2[( I 23.32-61 )/(G00-1 62.56)] 0.19 mm < 0.2mm= lienee Satisfactory. 0.I9w <0.2mm hence satisfactory DESIGN MAIN REINFORCEMENT FOR HOGGING MOMENT (TOP SLAB) Thickness of the slab = 600 mm BS5400 Part 4: 1990 M = 586 kNm/nrDesign bending moment, M design at mid span 586 kNm/m4.2.3 Assume severe environment condition, Cover Cover65 mm 65 mm Diametre of main reinforcement = 20 mm = 525 d = 525 mm= 600-65-20/2Effective depth, d mm M = (0.87fy)Asz z = (1 - l.lfyAs/fcubdJd equation 1 equation 5 BS 5400 Part 4: 1990 from these two equations 5.3.2.3 z = 0.5d[1+(1-5M/fcubd2)1/2l z = 0.5d [1+ (1-5x586x106/30x1000x5252)1/2 ] = 0.90 d < 0.950 d Hence o.k Z = 0.90 d = 0.900x525 = 473 mm Main reinforcement Ag = M / 0.87fyZ = 586x10® / 0.87x460x473 equation 1 mm2/m As= 3093 sreq 3093 mm2/m mm2 ) Agpro(As = 314220 @ 100Use T 3142 mm2/m Check for minimum reinforcement required for cantilever slab Check for minimum reinforcement 100AS / bad = 100x3142/(1000x525) BS 5400 Part 4:1990 5.8.4.1 Main reinforcement= 0.598 > 0.15 20 @ 100T Hence o.k OutputCalculationReference Serviceability Crack Check 466.35 kNmAt corners maximum service moment S3 From the above 0.071 162.56 mm 464.81 mm aep = x = z 6= 488.35 x 10 3142x464.81 = 334.386 N/mm2 fs = fses = 334.386 = 0.0017 200x103 = f h-x 1 x es Es d - x 162.56 x 0.0017600= 525 162.56 0.002 = ei - b(h-x)2 3EsAs(d-x) 1000 *(600- 162,56 )20.002— 3 x 200 X1000 x 3142 (525 -162.56) 0.0017 Calculation of aCT ^min “ 75 mm aCr = v 752+50.02 80.14 mm -10 ^cr SmWcr = I + 2[(aCP -cmin)/(h-x)] = 3x60.1 4x0.001 7Wcr I +2[(60.14-75)/(G00-1 G2.5G] 0.19 mm < 0.2mm= 0.1 9w = <0.2mm hence satisfactory Hence Satisfactory. 0.18% each face , each wayMinimum Steel 1080 mm2/m0.18 x 103 x 600Area == 100 (1149 mm2/m)Use Y16 @ 175mm centers Calculation OutputReference DESIGN FOR SHEAR Design shear force, V design = 1257 kN/m = 525Effective depth, d mm = V/bd = (1257x103)/(1000x525) = 2.39 N/mm2 = 0.75x(30)1/2 = 2.39 < 0.75x(fcu)1/2 Design shear stress, vBS 5400: Part 4: 1990 5.3.3.1 equation 8 v = 4.108 N/mm2 or 4.75 N/mm2 0.75X(fcu)1/2 Design shear stress, v 2.39 N/mm2 Hence O.K For uniaxial shear Allow, shear resistance £svc Where, depth ratio, = (0.27/ym)(100As/bwd)1,3(fcu)l,3^sBS 5400: Part 4: 1990 5.3.3.2 = (500/d)1/4 = (500/525)1'4 = 0.99 or 0.7 (greater value) = (0.27/0.99)x(100x3142/1000x525)v3x(30)1/3x1.25£svc = 0.89 < v = 2.39 N/mm2 Hence shear r/f is required DESIGN OF wall Consider load case 4.3 for design the wall of the culvert. Design main reinforcement for mid span of the slab. = 500Thickness of the slab mm Part 4: 1990 M = 1148 kNm/rr1148 kNm/mDesign bending moment, M design at mid span4.2.3 Assume severe environment condition, Cover Cover= 45 mm = 45 mm = 32Diametre of main reinforcement mm = 439 d - 439 mm= 500-45-32/2Effective depth, d mm 1 x'NM = (0.87fy)Asz z = (1 ■1.1fyA#/fcubd)d equation 1 equation 5 BS 5400 Part 4: 1990 4 Xfrom these two equations5.3.2.3 ' ftz = 0.5d[1+(1-5NI/fcubd2)1/2] z = 0.5d [1+ (1-5x1148x10e/30x1000x4392)1/2 ] = 0.543 d < b d Hence o.k Z = 0.543 d = 0.543x439 = 238 mm OutputCalculationReference Main reinforcement Ag = M / 0.87fyz = 1148x10® 7 0.87x460x238 equation 1 mm2/m As= 12032 req mm2/m12032 (As = 16085 mm2 ) AsUse T 32 @ 50 pro mm2/m16085 \S\ 16/17 \ W'V-'