Show simple item record

dc.contributor.author Jayalath, RAC
dc.date.accessioned 2011-06-11T04:26:12Z
dc.date.available 2011-06-11T04:26:12Z
dc.identifier.uri http://dl.lib.mrt.ac.lk/handle/123/1060
dc.description.abstract Determining a fair margin of risk that forms a part of mark-up in a bid is a crucial issue when pricing bill of quantities at a tender. The results indicates that risk is not adequately priced by almost all the local contracting firms but they often use experience, intuition, rule of thumb or guesswork. However, in the present day context of competitive business environment, it is time a new emphasis placed on identifying and assessing risk factor as precise as possible. Hence, the thesis is aimed to examine closely and objectively the risk factor involved in pricing construction projects and to propose a way of assigning a monetary value to the risk factor so as to arrive at a reasonable margin of risk and a contingency sum. At this exercise, various risk management techniques such as risk premium, sensitivity testing, monte-carlo simulation, utility theory, risk adjusted discount rate and expected monetary value etc have been commentated including their relative merits, demerits and practical limitations. Further, the contractual provisions as to apportionment of risk in tender and contract documents have also been discussed with special emphasis on ICTAD Conditions of Contract Revised in January 1989, conditions by which most of local building contract are governed. A statistical approach, one that is already developed, to decide on the sum of contingency allocation supported with a worked example extracted from building schedule' of rates is also suggested for the quantity surveyors to adopt in their pre-tender pricing exercises. The research concludes with a proposal of guidelines and recommendations on how to cope with the risk factor. It is the author's belief that these guidelines will benefit both construction contracting and consultancy firms.
dc.language.iso en en_US
dc.subject Thesis ; Dept. of Building Economics ; Estimating-Competitive Tendering
dc.title An Appraisal on pricing risk factor at tender stage
dc.type Thesis-Abstract
dc.identifier.faculty Engineering en_US
dc.identifier.degree MSc en_US
dc.identifier.department Department of Building Economics en_US
dc.date.accept 2000
dc.identifier.accno 72909 en_US


Files in this item

This item appears in the following Collection(s)

Show simple item record