Abstract:
Sri Lankan construction industry has been increased dramatically during last decade,
especially, road and highway construction is prominent among them. As per most of the
project, it was observed that there were variations with anticipated work condition, plan with
actual conditions. Sometimes, estimated project productivity could not be able to established
due to various reasons. This is identified “Disruption events” which loses the Contractor’s
money unnecessary. In this research, it was focused to identify sources of disruptions, record
maintenance and usage of disruption claim analysis methods in construction industry.
Questionnaire survey was carried out to identify status of disruption claim in construction
industry during last five years. A five point Likert scale where 1 represents ‘Not significant’
and 5 represents ‘Extremely significant’ was used at questionnaire survey to identify the
significance level among three main aspects such as sources of disruption, records
maintenance at site and usage of disruption claim analysis methods.
Overtime concurrent operation, additional quantities of work, delays, dilution of supervision,
joint occupancy, fast track construction, quality of craftsman, quality assurance/quality control
practice, labour wages, weather and economic activity in the area were highest significance of
causing disruption event in construction industry while stacking of trades, rework of already
installed work changes to the plans and specification, management control, site access, and
rework/errors were least impact. Further, it was found out that record keeping at site was
significantly maintained through payment certificate, labour time sheets and daily report.
However, it was identified that there was deficiency record maintenance of records such as
correspondence, change order log, separate cost account for specific change orders, and record
of change conditions caused by the owner even though those are important materials for
substantiation of claim. According to the analysis, submission of disruption claims in
construction industry with various types of disruption claim analysis methods was
considerably lower level. Documentary evidence widely used methods of measured mile
study, baseline productivity analysis and system dynamics modeling were least usage in
industry. Mostly used method was total cost method which can be easily prepared at available
data. Earned value analysis, comparison studies, industry based methods and modified cost
methods were used comparatively lower level than the total cost method.
Eventually, Contractor suffers from disruptions events due to deficiency of contemporary
records on hands. Therefore, it is recommended to establish one day before action plan, build
specialized teams on particular work, independent team to grab the work norms and head office
comments on project in order to answer disruptions early. Further, it is suggested to carry out
further research to find out suitable method for record tracking system in construction industry.