dc.description.abstract |
Construction procurement involves organizing processes of acquiring services and
products for activities starting from project investigation to completion of a project.
Along with the development of new concepts and technologies, construction procurement
arrangements were also developed to draw the best value for construction organizations.
Selecting the best procurement method for a specific project is a challenge since the
availability of diverse procurement options and subjective factors affecting the selection
of procurement methods. An inappropriate selection of a procurement method leads to
project failure while adversely affecting the expectation of stakeholders and the
economy. Since the number of steel building constructions are increasing in the Sri
Lankan context this study aims to identify factors which highly influence the selection of
a procurement method for steel building construction in Sri Lanka. In order to achieve
the aim, initially, a comprehensive literature survey was carried out to identify factors
which influence the procurement selection for building construction. Accordingly, 42
factors were identified. Subsequently, a quantitative research approach was followed to
list down the factors on their significance in selecting procurement method for steel
building construction in Sri Lanka. Consequently, 26 factors were concluded as the most
significant factors, which influence the procurement selection of steel building
construction through Relative Importance Index (RII). Procurement Path Decision
Chart was used to analyses the procurement selection factor and construction
management was identified as the most suitable procurement method for steel building
construction in Sri Lanka. |
en_US |
dc.language.iso |
en |
en_US |
dc.subject |
Procurement Methods |
en_US |
dc.subject |
Selection Criteria |
en_US |
dc.subject |
Steel Building Construction |
en_US |
dc.title |
Factors affecting the selection of a procurement method for steel building construction |
en_US |
dc.type |
Conference-Full-text |
en_US |
dc.identifier.faculty |
Architecture |
en_US |
dc.identifier.department |
Building Economics |
en_US |
dc.identifier.year |
2019 |
en_US |
dc.identifier.conference |
8th World Construction Symposium |
en_US |
dc.identifier.place |
Colombo |
en_US |
dc.identifier.pgnos |
340-349 |
en_US |
dc.identifier.email |
pubuduperera98@gmail.com |
en_US |
dc.identifier.email |
ra-maheshi@uom.lk |
en_US |
dc.identifier.email |
ukulatunga@uom.lk |
en_US |
dc.identifier.email |
suranga@uom.lk |
en_US |
dc.identifier.email |
mkcsw.mora@gmail.com |
en_US |
dc.identifier.doi |
doi.org/10.31705/WCS.2019.34 |
en_US |