Institutional-Repository, University of Moratuwa.  

Efficacy of adjudication as a dispute resolution mechanism : the case of road projects in Sri Lanka

Show simple item record

dc.contributor.advisor Gunatilake S
dc.contributor.author Palihawadana HI
dc.date.accessioned 2020
dc.date.available 2020
dc.date.issued 2020
dc.identifier.citation Palihawadana, H.I. (2020). Efficacy of adjudication as a dispute resolution mechanism : the case of road projects in Sri Lanka [Master's theses, University of Moratuwa]. Institutional Repository University of Moratuwa. http://dl.lib.uom.lk/handle/123/18814
dc.identifier.uri http://dl.lib.uom.lk/handle/123/18814
dc.description.abstract Disputes are unavoidable in construction projects due to their complex nature and could happen at any time. Unresolved disputes may prevent project from completing on time, within the budget and to the desired quality and lead ultimately to project failure. Arbitration has been used as the alternative dispute resolution mechanisms for many years in construction industry. However, over the years, since it is identified that even arbitration has become more time taking and disruptive to work progress, there was a necessity for a quicker dispute resolution mechanism, which helps to flow the work without getting disturbed. Fulfilling the above need, adjudication has been introduced and incorporated to the construction contracts as interim means of resolving disputes. Although, many researchers and authors identified several steps in order to conduct adjudication successfully, in Sri Lankan context it is experienced that adjudication continuously fail in achieving its objectives. Therefore, the study was focused on exploring how to enhance effectiveness of adjudication practice and identify the steps to be taken to adopting adjudication as an interim mechanism of dispute resolution in Sri Lankan context. The study was conducted through a multiple case study. In-depth study was carried out on four selected cases, representing both adjudication successfully and unsuccessfully concluded cases. Case study results were discussed in relation to the steps identified through literature review. Accordingly, (1) selecting dispute to adjudicate, (2) selecting adjudicators, (3) fair time to be fix, (4) establishing right to review and (5) establishing right to enforce and enforcement procedure of the adjudication process has been identified as failure points of conducting adjudication. Several issues as failure factors of adjudication has been identified in the aforesaid steps which are need to be address to achieve objectives of the adjudication. Identified failure factors were referred to three experts who involved in adjudication and got suggestions to overcome those failure facts. It is concluded that, in order to achieve the objectives of the adjudication in Sri Lankan construction industry, it is required to adopt full-term/stand-by dispute adjudication board from the commencement of projects, while providing better contractual provision when drafting the contract and establish proper mechanisms by the regulating authorities where it is necessary to address the identified issues. en_US
dc.language.iso en en_US
dc.subject CONSTRUCTION INDUSTRY - Road Development Projects en_US
dc.subject ADJUDICATION en_US
dc.subject INTERIM DISPUTE RESOLUTION MECHANISM en_US
dc.subject ROAD PROJECTS- Sri Lanka en_US
dc.subject CONSTRUCTION LAW AND DISPUTE RESOLUTION - Dissertation en_US
dc.subject BUILDING ECONOMICS - Dissertation en_US
dc.title Efficacy of adjudication as a dispute resolution mechanism : the case of road projects in Sri Lanka en_US
dc.type Thesis-Abstract en_US
dc.identifier.faculty Architecture en_US
dc.identifier.degree Master of Science in Construction Law and Dispute Resolution en_US
dc.identifier.department Department of Building Economics en_US
dc.date.accept 2020
dc.identifier.accno TH4518 en_US


Files in this item

This item appears in the following Collection(s)

Show simple item record