Show simple item record

dc.contributor.advisor Kariyawasam, C
dc.contributor.author Atukorala, NT
dc.date.accessioned 2011-05-24T04:56:44Z
dc.date.available 2011-05-24T04:56:44Z
dc.identifier.uri http://dl.lib.mrt.ac.lk/handle/123/794
dc.description.abstract The Galoya Irrigation Project is the first multipurpose Scheme started in Sri Lanka. The project was commissioned in the year 1956. After nearly over 20 yrs. of its existence the project was in a rather poor condition. The original project served an area of 45,000 Acs, however after over 23 yrs, Irrigation facilities were available only for nearly 32,500 Acs for Maha & 19,250 Acs for Yala. The Gal Oya rehabilitation project was funded by the USAID and commenced in 1980 and continued beyond 1985. This study analyses the impact of the project on the work done from 1980 to 1985 (Most of the work was done during this period) The study was centered mainly on the aspects connected to irrigation as delving into other areas of assessment would be a vast exercise. The Irrigation aspect covered the following fields and the findings are. a. The Social Aspect With the rehabilitation programme there was a turn around of behavior of farmers. For example vandalism was reduced to almost nothing. No structures were damaged and no bunds cut. Third parties were not approached regarding water issues. Cultivation-calendar was adhered to as planned at the cultivation meetings. b. Water management and duty of water Rehabilitation of the project successfully improved a. The water conveyance capacity b. The water control capacity c. The water measurement capacity The foregoing enabled a very effective water management programme to be introduced and is being followed even today. This involved a computer programme with a very satisfactory feedback system. A number of water control structures were installed where necessary enabling the optimum use of water and preventing wastage. This measure improved the duty of water from pre-project value of 5.2 acft/Ac to the post project figure of 3.68 acft/Ac. c. Paddy production There was a gradual increase in the acreage and the Yield /Ac as the project progressed. The total acreage increased from pre-project 19,250 Acs Yala to post-project 53,000 Ac s Yala in 1985. Maha Acreages were pre-project 32,500 Acs to post-project 53,000 Acs. The increase in yield was pre project 34 bushels/Ac in 1979 to post project 60 bushels/Ac in 1985. The Yield is expected to increase further with the increase in confidence in the delivery schedules of water prompting greater agronomic imputs & increased labour inputs. Incidentally the yield in 1986 was 66.4 bushels/Ac. and in 1987 it was 70.5 bu. shels,/Ac. d. Economic Evaluation An economic evaluation was done taking into account only the increase in production of paddy and the .IRR was found to be 33.8%. However when the impact of the project as a whole is considered the fact that this project has raised the standard of living of the farmers within the project, created a sense of civic obligation among them together with a spin off of additional employment etc. cannot be underscored thus enabling this rehabilitation project as an example suitable for imitation in other rehabilitation projects to be taken up in the future.
dc.language.iso en en_US
dc.subject MEng in Land & Water Development Engineering
dc.subject IRRIGATION
dc.subject Water Management Problems
dc.title A preliminary assessment of the Gal Oya water management project
dc.type Thesis-Abstract
dc.identifier.faculty Engineering en_US
dc.identifier.degree MSc en_US
dc.identifier.department Department of Civil Engineering en_US
dc.date.accept 1987
dc.identifier.accno 52179 en_US


Files in this item

This item appears in the following Collection(s)

Show simple item record