Establishing schedule quality parameters for effective delay analysis in construction projects

dc.contributor.authorBaskar, S
dc.contributor.authorJagannathan, M
dc.contributor.authorUbhayakar, DK
dc.contributor.authorHariharan, K
dc.contributor.editorWaidyasekara , KGAS
dc.contributor.editorJayasena, HS
dc.contributor.editorWimalaratne, PLI
dc.contributor.editorTennakoon, GA
dc.date.accessioned2025-09-22T04:20:16Z
dc.date.issued2025
dc.description.abstractThe construction industry is vital to national development, yet it often faces inefficiencies due to time and cost overruns, largely stemming from a variety of factors. These delays lead to project disruptions, disputes, and claims. Various delay analysis methods—categorized as prospective and retrospective—are employed to manage and mitigate such delays. However, the success of these methods highly relies on the quality of the project schedule. While general schedule quality parameters exist, there has been limited focus on parameters specific to delay analysis. This study investigates preferred delay analysis approaches and identifies challenges in their application. A survey and focus group study involving real-time projects established key schedule quality parameters for delay analysis. These include: Sequencing of Activities, Inclusion of All Activities, Use of Lags, Use of Non-Finish-to-Start Relationships, Date Constraints, and Float Colour Coding. Among these, “Inclusion of All Activities” emerged as the most critical, while the “Use of Lags” was found to be the least sensitive parameter. By highlighting these parameters, the study provides valuable insights for practitioners to enhance schedule robustness. A well-structured schedule allows for accurate prospective delay analysis, helping mitigate potential time as well as cost overruns and improving overall project performance.
dc.identifier.conferenceWorld Construction Symposium - 2025
dc.identifier.departmentDepartment of Building Economics
dc.identifier.doihttps://doi.org/10.31705/WCS.2025.50
dc.identifier.emailce23m123@smail.iitm.ac.in
dc.identifier.emailmuralij@civil.iitm.ac.in
dc.identifier.emailkdmdheeraj@lntecc.com
dc.identifier.emailkhariharan@lntecc.com
dc.identifier.facultyArchitecture
dc.identifier.issn2362-0919
dc.identifier.pgnospp. 664-676
dc.identifier.placeColombo
dc.identifier.proceeding13th World Construction Symposium - 2025
dc.identifier.urihttps://dl.lib.uom.lk/handle/123/24168
dc.language.isoen
dc.publisherDepartment of Building Economics
dc.subjectDelay Analysis
dc.subjectProspective Delay Analysis
dc.subjectSchedule Quality Parameters
dc.subjectSensitivity Analysis
dc.titleEstablishing schedule quality parameters for effective delay analysis in construction projects
dc.typeConference-Full-text

Files

Original bundle

Now showing 1 - 1 of 1
Loading...
Thumbnail Image
Name:
50. S17066.pdf
Size:
881.79 KB
Format:
Adobe Portable Document Format

License bundle

Now showing 1 - 1 of 1
Loading...
Thumbnail Image
Name:
license.txt
Size:
1.71 KB
Format:
Item-specific license agreed upon to submission
Description:

Collections