Suitability of Criteria for Selecting a Delay Analysis Technique Suitable to Analyse Delays in Road Construction Projects in Sri Lanka

dc.contributor.authorEkanayake, EMK
dc.contributor.authorPerera, BAKS
dc.date.accessioned2015-08-24T11:53:43Z
dc.date.available2015-08-24T11:53:43Z
dc.date.issued2015-08-24
dc.description.abstractDelays in construction projects are inevitable and they are the most critical factor that affects the cost of a construction project. They have to be analyzed comprehensively using appropriate techniques so as to identify their impacts. This study was carried out to find out, the delay analysis techniques (DAT) that are used most commonly in road projects in Sri Lanka, the extent of their usage, problems that arises when they are used and the criteria for selecting a suitable technique. The research methodology adopted involved an extensive literature review, interviews and a questionnaire survey. The most commonly used DATSs were identified through the literature review and by interviewing four practitioners. A questionnaire survey was carried out among a group of 60 professionals selected through purposive sampling. It was found that five types of delay analysis techniques are mainly used in Sri Lanka to determine the delays encountered in road projects and the most commonly used such technique is the as-planned vs as-built analysis while the least used is the window analysis. The nonavailability of professionals to analyze delays is found to be the main problem and acceptance by courts and tribunals is the most important criteria (out of nine identified criteria) used in selecting a delay analysis technique.en_US
dc.description.sponsorshipInternational Council for Research and Innovation in Building and Construction (CIB)en_US
dc.identifier.conferenceThe 4th World Construction Symposium 2015en_US
dc.identifier.departmentMinistry of Infrastructure Audit, Omanen_US
dc.identifier.departmentDepartment of Building Economics, University of Moratuwa, Sri Lankaen_US
dc.identifier.facultyEngineeringen_US
dc.identifier.pgnospp. 449-457en_US
dc.identifier.placeColomboen_US
dc.identifier.proceedingSustainable Development in the Built Environment: Green Growth and Innovative Directionsen_US
dc.identifier.urihttp://dl.lib.mrt.ac.lk/handle/123/11255
dc.identifier.year2015en_US
dc.language.isoenen_US
dc.subjectAs-Planned vs As-Built Analysisen_US
dc.subjectCriteria
dc.subjectDelay Analysis Techniques.
dc.titleSuitability of Criteria for Selecting a Delay Analysis Technique Suitable to Analyse Delays in Road Construction Projects in Sri Lankaen_US