Time overrun events accountable to the client in bridge construction projects, Sri Lanka

dc.contributor.advisorSiriwardana C
dc.contributor.authorLakshamana NWH
dc.date.accept2022
dc.date.accessioned2022
dc.date.available2022
dc.date.issued2022
dc.description.abstractThe bridge construction industry in Sri Lanka has been severely affected by the time overrun events in the past. The trend is continuing and the requirement of taking mitigation measures in the industry is a high priority. Once a time overrun event occurs, it will be analysed by the consultant of the contract. If the accountability of it is on the client, the contractor will be granted an Extension of Time and the relevant compensations. Therefore, identifying the causes of the time overrun events and the accountable party of those is a high necessity for forecasting and taking mitigation measures. The research is on identifying the key time overrun events accountable to the client in bridge construction projects, Sri Lanka. Seventy (70) time overrun events in bridge construction projects have been found by literature review and case studies of 18 projects. These time overrun events are analysed from the responses by the professionals through a questionnaire survey and found out nineteen (19) time overrun events accountable to the client using the Relative Importance Index. The analyses have been continued through interviews with the key experts of the field as well to understand the probability and impact of the events. Accordingly, by using the Frequency Index and Severity Index, the events were prioritized and the use of Probability-Impact Matrix, it has been identified the five (5) most critical events accountable to the client in the bridge construction projects which are Possession of site, Unclear scope (Variation Orders), Land acquisition matters, Utility shifting matters and Design changes. Further, it has been observed that around 70% of time overrun events accountable to the client can be forecasted in the planning phase (before awarding the contract) of the project. Therefore, the research recommends several methods for conducting a proper planning phase of a project by highlighting the current drawbacks and hence avoiding or mitigating the risk of time overrun events that would be generated during the construction phase of the project.en_US
dc.identifier.accnoTH4984en_US
dc.identifier.citationLakshamana, N.W.H. (2022). Time overrun events accountable to the client in bridge construction projects, Sri Lanka [Master's theses, University of Moratuwa]. Institutional Repository University of Moratuwa. http://dl.lib.uom.lk/handle/123/21616
dc.identifier.degreeMSc In Construction Project Managementen_US
dc.identifier.departmentDepartment of Civil Engineeringen_US
dc.identifier.facultyEngineeringen_US
dc.identifier.urihttp://dl.lib.uom.lk/handle/123/21616
dc.language.isoenen_US
dc.subjectTIME OVERRUNen_US
dc.subjectACCOUNTABILITYen_US
dc.subjectCLIENTen_US
dc.subjectMITIGATION MEASURESen_US
dc.subjectRELATIVEIMPORTANCE INDEXen_US
dc.subjectCONSTRUCTION COMPANIES - Sri Lankaen_US
dc.subjectBRIDGE CONSTRUCTIONen_US
dc.subjectCIVIL ENGINEERING -Dissertationen_US
dc.subjectCONSTRUCTION PROJECT MANAGEMENT- Dissertationen_US
dc.titleTime overrun events accountable to the client in bridge construction projects, Sri Lankaen_US
dc.typeThesis-Abstracten_US

Files