The Appropriate delay analysis techniques to analyze the delays in road construction projects in Sri Lanka

dc.contributor.advisorPerera, BAKS
dc.contributor.authorEkanayaka, EMK
dc.date.accept2014-12
dc.date.accessioned2019-01-23T00:25:28Z
dc.date.available2019-01-23T00:25:28Z
dc.description.abstractThe Appropriate Delay Analysis Techniques to Analyze the Delays in Road Construction Projects in Sri Lanka Most of the road constructions projects are unable to complete within the scheduled time and consequently subject to delay. These delays are compensated by the client and the contractor or either party as appropriate. In order to quantify the amount of time of delay and the apportionment of delay to the respective parties/party a proper delay analysis has to be carried out. It is evident that currently some ad hoc methods are followed for this purpose. Therefore it is the high time to identify the most suitable technique to analyze the delays in road construction projects in Sri Lanka. This study is aiming to identify the most suitable delay analysis technique to analyze the delays in road construction projects in Sri Lanka. The descriptive study was carried out through a preliminary survey, questionnaire survey and detailed interviews among the practitioners of the industry. The data was analyzed using percentages on frequencies, relative importance index and mean ratings. Criterion suitability score and overall suitability scores were calculated to decide the most suitable delay analysis techniques. The study revealed that, 66% of the projects in the study sample were delayed and DATs were used in 87.5% of them. As planned v as built method is the mostly used DAT. Unavailability of experts and difficulties in collecting reliable information were the main problems. Nine criteria which influenced in selecting a DAT were identified and the acceptance by the courts and tribunals was the mostly influenced criteria. The window analysis method which scored highest OSS was recommended as the most suitable method to analysis the delay in road projects in Sri Lankaen_US
dc.identifier.accno108978en_US
dc.identifier.citationEkanayaka, E.M.K. (2014). The Appropriate delay analysis techniques to analyze the delays in road construction projects in Sri Lanka [Master's theses, University of Moratuwa]. Institutional Repository University of Moratuwa. http://dl.lib.mrt.ac.lk/handle/123/13827
dc.identifier.degreeMaster of Science in Construction Law and Dispute Resolutionen_US
dc.identifier.departmentDepartment of Building Economicsen_US
dc.identifier.facultyArchitectureen_US
dc.identifier.urihttp://dl.lib.mrt.ac.lk/handle/123/13827
dc.subjectDelay Analysis Techniquesen_US
dc.subjectRoad Construction Projectsen_US
dc.subjectWindow Analysis Methoden_US
dc.subjectTime Impact Analysis Methoden_US
dc.titleThe Appropriate delay analysis techniques to analyze the delays in road construction projects in Sri Lankaen_US
dc.typeThesis-Abstracten_US

Files

Original bundle

Now showing 1 - 3 of 3
Loading...
Thumbnail Image
Name:
108978-1.pdf
Size:
280.44 KB
Format:
Adobe Portable Document Format
Description:
Pre Text
Loading...
Thumbnail Image
Name:
108978-2.pdf
Size:
374.61 KB
Format:
Adobe Portable Document Format
Description:
Post Text
Loading...
Thumbnail Image
Name:
108978.pdf
Size:
789.32 KB
Format:
Adobe Portable Document Format
Description:
Full Thesis