Optimization of soot blowing operation for Lakvijaya coal power plant in Sri Lanka

dc.contributor.advisorAttalage RA
dc.contributor.authorSarathkumara SCM
dc.date.accept2020
dc.date.accessioned2020
dc.date.available2020
dc.date.issued2020
dc.description.abstractAn optimization of soot blowing operation was carried out for Unit No.3 for Lakvijaya Power Plant in Sri Lanka. Average coal flow rate and flue gas temperature are the key indicators of boiler performance with soot blowing process. In accordance with ASMI PTC 4-1998, a mathematical modeling tool was developed to determine the boiler efficiency in present condition and different frequencies of soot blowing. The maximum efficiency of the boiler was determined as 79.76% at soot free condition. An equation was derived to express the relationship between input fuel consumption and soot blowing frequency. Maximum fuel cost saving can be achieved in between the frequency of 24 hours and 34 hours with respect to the normal operation of routing of soot blowing. Same frequency range gives the maximum cost saving in terms of effective cost. Considering the practical applicability daily soot blowing schedule is recommended.en_US
dc.identifier.accnoTH4396en_US
dc.identifier.citationSarathkumara, S.C.M. (2020). Optimization of soot blowing operation for Lakvijaya coal power plant in Sri Lanka [Master’s theses, University of Moratuwa]. Institutional Repository University of Moratuwa. http://dl.lib.uom.lk/handle/123/16636
dc.identifier.degreeM.Eng. in Energy Technologyen_US
dc.identifier.departmentDepartment of Mechanical Engineeringen_US
dc.identifier.facultyEngineeringen_US
dc.identifier.urihttp://dl.lib.uom.lk/handle/123/16636
dc.language.isoenen_US
dc.subjectENERGY TECHNOLOGY – Dissertationsen_US
dc.subjectMECHANICAL ENGINEERING – Dissertationsen_US
dc.subjectSOOT BLOWINGen_US
dc.subjectBOILER PERFORMANCEen_US
dc.subjectFLUE GAS TEMPERATUREen_US
dc.subjectMATHEMATICAL MODELINGen_US
dc.subjectPOWER PLANT - Sri Lankaen_US
dc.titleOptimization of soot blowing operation for Lakvijaya coal power plant in Sri Lankaen_US
dc.typeThesis-Full-texten_US